 5.      Which of these Agile Manifesto elements need to be replaced?

(A)      Responding to change over following a plan
(B)      Customer collaboration over conflict management
(C)      Working software over comprehensive documentation
(D)      Individuals and interactions over processes and tools
 


 
Answer B

Description

Why (B): It should read as "Customer collaboration over contract negotiations"
Why NOT (A), Why NOT (C), Why NOT (D): All these are correct as per the Agile Manifesto

Reference

 Agile Project Management with Scrum, Ken Schwaber