 4.      Agile methods consist of individual elements called practices.  Which of these is NOT a practice followed in XP?

(A)      Using version control for code management
(B)      Setting coding standards for the team to follow
(C)      Test first development in coding
(D)      Weekly code integration
 


Answer D

Description

Why (D): Code integration occurs as often as possible, either hourly or atleast daily 
Why NOT (A), Why NOT (B), Why NOT (C): These are all XP practices 


Reference

The Art of Agile Development - James Shore & Shane Warden, chap 2, page 9