  1. Mr Aaron, the Senior Manager in your company performs strategic planning, which is focused on the long term.  You as the Project Manager in this company, perform tactical planning, which is focused on the short term towards achieving a goal.  Which one of the following techniques implements this strategic and tactical planning approach in a project?

(A)      Release planning, iteration planning
(B)      Iteration planning, agile planning
(C)      Detailed planning, test first planning
(D)      Release planning, portfolio planning
 

 
Answer A

Description

Why (A): This is the correct order, with release planning for long term and iteration planning for the short term
Why NOT (B):  There is no such thing as just 'agile planning'
Why NOT (C):  This option does not provide sufficient justification
Why NOT (D):  The order is reversed, with portfolio planning for the long haul and release planning for the short haul

Reference

The Software Project Manager’s Bridge to Agility, Michele Sliger & Stacia Broderick, chap 6